The West Yorkshire Combined Authority had generated funding for an improved cycle link across the city to connect existing routes out to the A64 and A65. This was in light of the requirement to reduce disruption in the city. A key contract for Colas, the scheme developed our business profile and ability to tender for similar projects of similar size whilst further enforcing our relationship with Leeds City Council as a contractor that ‘saved the day’.


£4.2m

Project value



Approach

  • Aimed to carry out work in best interests for all
  • Took a 'non-contractual' approach
  • Liaised closely with Leeds Network Management
  • Established requirements for cities road network to minimise disruption
  • Project divided into three sections:
  • Section A – Eastern sections linking Quarry Hill and Marsh Lane to Crown Point Bridge and Kirkgate
  • Section C – Western section connecting the Leeds end of Phase 1 at Gotts Road to City Square
  • Section D – From Wellington Street to George Street